Spur repair task gathers momentum

Posted on 29 May 2009 by editor

SUNSARI, May 29 - After flood in the Koshi River breached the three temporary cofferdams constructed to alter the river’s course on Tuesday night, the Indian contractor has speeded up reconstruction and repair work on the spurs and embankment from Thursday afternoon.

Sheetal Babu Regmi, joint secretary at the Ministry of Water Resources (MoWR), who is at the Koshi site said, Basistha and Basistha, the Indian contractor has started reconstruction and repair work as the water level in the river started decreasing after  rain stopped from Thursday afternoon.

On Thursday afternoon about 64,000 cusecs water was flowing in the river while it was 95,000 cusecs on Wednesday afternoon. About 160,000 cusecs water was flowing during the flood last year.

Flood resulting from incessant rain for almost five days had breached the three cofferdams and one pilot channel constructed to divert the Koshi waters towards the barrage on Tuesday night.

Following the breach, the main course of the river diverted towards the eastern side where reconstruction work on the embankment was going on, raising possible threat of inundation after three spurs built along the embankment started eroding, according to officials.

The Indian government has stated constructing five spurs along the 1,700-metre stretch of the Koshi embankment, which is expected to be completed by June 15. However, Nepali officials blame the snail-paced work of Basistha and Basistha and are sceptical that the reconstruction will be completed by the given date. Out of five spurs to be constructed by the Indian side, only three spurs have been constructed till date.

The spurs were constructed to tame the river before this year’s monsoon sets in, according to officials.

According to Ramesh Kulkarni, project manager of Basistha and Basistha, the reconstruction of spurs, which had started eroding after the cofferdams were breached on Tuesday night, has started.

Reconstruction and repair of the damaged spurs will be completed in the next four days and reconstruction of the embankment will speed up after that, he said. A high level team comprising officials of Nepal and India directed the Indian side to speed up reconstruction work after visiting the affected site on Wednesday.

Meanwhile, Bijendra Prasad Yadav, Water Resources minister of Bihar state, India, on Thursday blamed the lack of security provided by Nepal for delay in reconstruction of the destroyed Koshi embankment .

Yadav, who was on a field visit at the site on Thursday said, “Nepal lacked security for the Indian contractor who faced frequent attacks time and again. The frequent obstructions carried out by locals has delayed reconstruction work.”

Comments (0)

Photo Feature

Guest Column

    Mahakali Treaty outcome of economic nationalism

    By Hari Bansh Jha

     It was on 12 February 1996 that the the Nepalese Prime Minister Sher Bahadur Deuba and the then Indian Prime Minister P.V. Narsimha Rao signed an agreement on the integrated development of the Mahakali river in Delhi. The Pancheshwor Project under the Treaty was expected to produce 6,000 MW of hydro-power with the investment cost [...]

    Details

Interview

    No alternative to power purchase from India : Mahat

    The meeting of the Joint Commission on Water Resources is scheduled for the first week of November and is to be followed soon after by ministerial-level talks that will take up all issues relating to the setting up of the Pancheshwar Development Authority and reach a conclusion. We have informally agreed to locate PDA headquarters in Nepal

    Details

Opinoin Tank

    Pain of Losing West Seti

    By Sudheer Raj Sharma Dhakal

    The well-versed 750 MW West Seti Hydroelectric Project (WSHP) is once again capturing major energy headlines in both the print and electronic media of Nepal. Looked as a porthole for the development of the Far Western Development Region (FWDR) that has received the least development privilege, this project has been lingering for more than a [...]

    Details

Polls

  • चीन र नेपालकका यूवाहरु एक अर्काका देशमा भ्रमण गर्न पाउने सम्झौता तपाईलाई कस्तो लाग्यो ?

    View Results

    Loading ... Loading ...
Polls Archive